In 2010, FGC UES will begin construction of seven facilities in the Far East

In 2010, OAO “UES FGC” will introduce an additional 50 MVA transformer capacity and 391 miles of transmission lines in the Far East. This will result in significantly improved reliability of electricity supply of the five subjects of the RF with a population of about 5 million, secured connection to the network objects summit of the Asia-Pacific Economic Cooperation (APEC) to be held in 2012 in Vladivostok, as well as the main pipeline East Siberia - Pacific Ocean , the company reported.

As part of the energy of the ring of 500 kV Far East - Vladivostok - Lozovaya - Chuguevka length of 467 km in 2010, a branch of OJSC “FGC UES - Trunk Power Grids (MEA), East continue construction in Primorye 500 kV substation Lozova capacity of 501 MVA . Entering the new substation in operation, planned for 2012, would eliminate the power shortage in the southern part of the Far Eastern power grid and ensure the functional reliability of 220 kV networks in the Primorsky Territory. In addition, the substation will provide electricity Lozova oil port in the Bay Kozmino (ESPO).

In the second quarter of 2010 in Yakutia East MEA complete construction of the second circuit 220 kV transmission line Neryungri GRES - Lower Kuranakh length of 275 km. The new chain will increase the reliability of electricity consumers Neryungri and Aldan regions of Yakutia, including large-scale gold-mining enterprises of the republic, as well as oil pumping station ESPO oil pipeline system.

Under the Federal Program “Development of Vladivostok as a center of international cooperation in the Asia-Pacific region will begin construction of new substations of 220 kV - Patroclus and Russian - with a capacity of 126 MVA each. In the second quarter of 2010 is scheduled to begin construction of 220 kV transmission line Green Corner - Russian length of 18 km, including 220 kV cable passage through the Bosporus East, as well as substations of 220 kV green corner. Entering these power projects in operation is scheduled for December 2011.

To modernize the airport of Vladivostok - Knevichi in March 2010 to commence construction of substation 220 kV airport capacity of 50 MVA. Completion is scheduled for the third quarter of 2010. The new substation will provide electricity Extensible airport.

This year MEA East to begin construction in the Amur region power line 220 key - Magdagachi designed to improve the reliability of power supply to consumers the western part of the Amur region, as well as lines of 500 kV Amur - State border.

In addition, in 2010, will continue a comprehensive reconstruction of the five substations 220 kV: Central District (RC) in the Khabarovsk Territory, Tynda in the Amur region, the Coast-2, Broad and Spassky in the Primorsky Territory. As a result of technical upgrading bc75y 2012 facilities will meet the modern requirements.

MEA East serve the Khabarovsk and Primorsky Territories, Amur Oblast, Jewish Autonomous Region, as well as the south of the Republic of Sakha (Yakutia), the total area of about 2 million square feet. km and a population of 4.8 million people. In the operation of the branch are 12 526 km of transmission lines 220-500 kV, 64 substations of 220 kV and 500 kV substations of seven.
Course currency basket to the ruble on Tuesday rose by 0.52% to 35.913 rubles
MICEX index compared with the value at closing of the previous trading day decreased by 1.998%
Reducing Russia”s stock market will soon end
Downward trends in the market may be continued in the near future
In 2009 inflation in Russia is 6 times higher than the growth in consumer prices in Europe
NBU notes the failure of several banks” plans to increase capital in 2009
If tomorrow the statistics from the U.S. will be positive, Russia”s stock exchanges will continue to move upwards
As a result of trading the MICEX index lost 2.19%, ending the day at 1,384.79 points
Until the end of this week the market of Russia will consolidate in the region of 1 400 points mark for the MICEX



Leave a Reply
\